Concrete Cubic Meter Calculator

Concrete is ordered by the cubic meter in most of the world. Enter your dimensions in meters, centimeters or millimeters and get the m³ to order, with yd³ and ft³ alongside and the weight in kilograms.

  • Free
  • No sign-up
  • Math shown
  • Sources listed

Your measurements

Quick sizes

How many identical pieces

%

5–10% is the usual advice. Use more when the subgrade is uneven, forms may flex or spillage is likely.

Advanced assumptions

Yields come from the bag label or data sheet. Check yours: other products (high-strength, lightweight) differ.

Order about2.20 m³2.88 yd³ · 77.69 ft³ · includes 10% waste

Above 2 yd³ ready-mix is usually the better choice. Hand-mixing 130 bags is a long day. Small truck orders often carry a short-load fee, so ask your plant.

Example for the numbers in the form. Change any value to calculate your own.

Volume

Net volume
2.616 yd³
Net volume
70.63 ft³
Net volume
2.000 m³
Order (with waste)
2.88 yd³

Bagged mix (80/60/50/40 lb)

80 lb bags
130
60 lb bags
173
50 lb bags
208
40 lb bags
259

Weight of the order

Pounds
11,654 lb
US tons
5.83
Kilograms
5,286 kg
Density used
150 lb/ft³

Wheelbarrow loads

3 ft³ barrow
26 loads
6 ft³ barrow
13 loads

Material cost (estimate)

Ready-mix + short load
$410 – $961
Bagged (80 lb)
$715 – $1,040

Ranges, last verified 2026-10-04. Excludes labor, forms and finishing.

Next: plan the rest of the pour

These open with your measurements already filled in.

By the Editorial team · How we calculate · Updated Oct 4, 2026

Show the math
  1. Convert to feet (inches ÷ 12, centimeters ÷ 30.48): Length 5 m = 16.4042 ft; Width 4 m = 13.1234 ft; Thickness 100 mm = 0.3281 ft
  2. Volume = 16.4042 × 13.1234 × 0.3281 × 1 = 70.6293 ft³
  3. Net volume = 70.6293 ft³ ÷ 27 = 2.6159 yd³ (× 0.0283168 = 2 m³)
  4. Order quantity = 2.6159 yd³ × (1 + 10%) = 2.8775 yd³ = 77.6923 ft³
  5. 80 lb bags = 77.6923 ft³ ÷ 0.6 ft³ per bag = 129.49 → 130 bags (always round up)
  6. Weight = 77.6923 ft³ × 150 lb/ft³ = 11,654 lb

How to measure

Measure the length and width of the formwork in meters, and the thickness in millimeters or centimeters. Thickness is the dimension most often confused: 100 mm is 0.1 m, not 1 m. The calculator converts each unit exactly, so you can leave dimensions in whichever unit you measured.

For slabs poured over a rough or sloping base, take several thickness readings and use their average.

Slab length, width and thicknessLength (L)Width (W)Thickness (T)
Volume in cubic meters = length (m) × width (m) × thickness (m).

The cubic meter formula

Work in meters and multiply: length × width × thickness. Convert thickness from millimeters by dividing by 1,000, so 100 mm is 0.1 m. The answer is cubic meters. Plants sell ready-mix by the cubic meter, often in steps of 0.5 m³ and with a minimum load size, so round your answer up and ask the plant for its minimum.

Add a waste allowance. In metric countries 5 to 10% is typical for a slab on a prepared base, and more for trench footings, where the excavation is rarely neat.

Formula: V (m³) = L (m) × W (m) × T (m) × quantity × (1 + waste%).

Worked example: 5 × 4 m slab, 100 mm thick

  1. Convert to feet (inches ÷ 12, centimeters ÷ 30.48): Length 5 m = 16.4042 ft; Width 4 m = 13.1234 ft; Thickness 100 mm = 0.3281 ft
  2. Volume = 16.4042 × 13.1234 × 0.3281 × 1 = 70.6293 ft³
  3. Net volume = 70.6293 ft³ ÷ 27 = 2.6159 yd³ (× 0.0283168 = 2 m³)
  4. Order quantity = 2.6159 yd³ × (1 + 10%) = 2.8775 yd³ = 77.6923 ft³
  5. 80 lb bags = 77.6923 ft³ ÷ 0.6 ft³ per bag = 129.49 → 130 bags (always round up)
  6. Weight = 77.6923 ft³ × 150 lb/ft³ = 11,654 lb
5 × 4 m, 100 mm thick, 10% waste
QuantityResult
Net volume2.616 yd³ (70.63 ft³, 2.000 m³)
Order with 10% waste2.88 yd³ (2.20 m³)
80 lb bags130
60 lb bags173
Weight at 150 lb/ft³11,654 lb

You would order about 2.20 m³. In US units that is 2.88 yd³ or 77.69 ft³. At 150 lb/ft³ (about 2,400 kg/m³) the order weighs 5,286 kg.

Concrete per square meter

Volume per square meter of slab
Thicknessm³ per m²Area per m³
75 mm0.07513.33 m²
100 mm0.10010.00 m²
125 mm0.1258.00 m²
150 mm0.1506.67 m²
200 mm0.2005.00 m²

The table is useful for quoting a floor by area: a 100 mm slab uses 0.1 m³ for every square meter, so 1 m³ covers 10 m². At 150 mm it covers only 6.67 m².

Converting between metric and US volumes

Unit conversions used by this site
FromToMultiply by
m³yd³1.30795
m³ft³35.3147
m³litres1,000
yd³m³0.764555
ft³m³0.0283168
kg/m³lb/ft³0.062428

The foot-to-meter factor is exact (0.3048 m), and the cubic factors follow from it. See the methodology page for the sources.

Cement, sand and gravel by volume

If you are mixing on site rather than ordering a truck, the mix ratio calculator turns a cubic meter of concrete into cement bags, sand and gravel. It uses the standard dry-volume factor of about 1.54, because the dry materials occupy more space than the wet concrete they make.

Mistakes with metric volumes

  • Entering thickness in meters when you measured millimeters.
  • Mixing meters and centimeters in one calculation.
  • Forgetting that 1 m³ is not 1 yd³. A cubic meter is 1.31 cubic yards.
  • Ordering exactly the net volume with no allowance for the base and the forms.
  • Not accounting for the minimum load charged by the plant.

Ordering by the cubic meter

In most countries plants sell concrete in cubic meters, often in half-meter steps. State the quantity, the strength class (such as C25/30) and the maximum aggregate size when you order, and ask about the minimum load and the delivery charge.

Frequently asked questions

How do I calculate cubic meters of concrete?

Multiply length, width and thickness in meters. A 5 × 4 m slab, 100 mm thick: 5 × 4 × 0.1 = 2 m³.

How many cubic meters in a cubic yard?

One cubic yard is 0.764555 m³. One cubic meter is 1.30795 yd³.

How much does a cubic meter of concrete weigh?

About 2,400 kg for normal-weight concrete, which is 150 lb/ft³. Real mixes range from about 2,240 to 2,400 kg/m³.

How much area does 1 m³ of concrete cover?

At 100 mm thick, 10 m². At 150 mm, 6.67 m². At 200 mm, 5 m².

How much waste should I add in metric?

Five to ten percent for slabs on a prepared base, more for trenches and uneven ground.

Does the calculator show US bag counts?

Yes. The result card includes 40, 50, 60 and 80 lb bag counts alongside the metric volume, because the same pages are used for US and metric projects.

Sources

Estimate only. Results depend on the numbers you enter, ground conditions and your supplier. For structural work consult a licensed engineer and follow local codes. Brand names such as Quikrete and Sakrete are used only to cite published product data. This site is not affiliated with any brand.

Order about2.20 m³

↑↓ to move Enter to open Esc to close

Share this page

On this page

My Pour List