Concrete Curb and Gutter Calculator

A curb with a gutter is one long, constant cross-section. Enter the section dimensions in inches and the length in feet to get the concrete for the run.

  • Free
  • No sign-up
  • Math shown
  • Sources listed

Your measurements

Quick sizes

How many identical pieces

%

5–10% is the usual advice. Use more when the subgrade is uneven, forms may flex or spillage is likely.

Advanced assumptions

Yields come from the bag label or data sheet. Check yours: other products (high-strength, lightweight) differ.

Order about5.09 yd³3.89 m³ · 137.50 ft³ · includes 10% waste

Above 2 yd³ ready-mix is usually the better choice. Hand-mixing 230 bags is a long day. Small truck orders often carry a short-load fee, so ask your plant.

Example for the numbers in the form. Change any value to calculate your own.

Volume

Net volume
4.630 yd³
Net volume
125.00 ft³
Net volume
3.540 m³
Order (with waste)
5.09 yd³

Bagged mix (80/60/50/40 lb)

80 lb bags
230
60 lb bags
306
50 lb bags
367
40 lb bags
459

Weight of the order

Pounds
20,625 lb
US tons
10.31
Kilograms
9,355 kg
Density used
150 lb/ft³

Wheelbarrow loads

3 ft³ barrow
46 loads
6 ft³ barrow
23 loads

Material cost (estimate)

Ready-mix + short load
$687 – $1,393
Bagged (80 lb)
$1,265 – $1,840

Ranges, last verified 2026-10-04. Excludes labor, forms and finishing.

Next: plan the rest of the pour

These open with your measurements already filled in.

By the Editorial team · How we calculate · Updated Oct 4, 2026

Show the math
  1. Convert to feet (inches ÷ 12, centimeters ÷ 30.48): Curb depth 6 in = 0.5 ft; Curb height 6 in = 0.5 ft; Gutter width 18 in = 1.5 ft; Flag thickness 6 in = 0.5 ft; Length 100 ft
  2. Curb section = 0.5 × 0.5 = 0.25 ft²
  3. Flag section = (0.5 + 1.5) × 0.5 = 1 ft²
  4. Volume = (0.25 + 1) × 100 × 1 = 125 ft³
  5. Net volume = 125 ft³ ÷ 27 = 4.6296 yd³ (× 0.0283168 = 3.5396 m³)
  6. Order quantity = 4.6296 yd³ × (1 + 10%) = 5.0926 yd³ = 137.5 ft³
  7. 80 lb bags = 137.5 ft³ ÷ 0.6 ft³ per bag = 229.17 → 230 bags (always round up)
  8. Weight = 137.5 ft³ × 150 lb/ft³ = 20,625 lb

How to measure

Curb depth is the horizontal thickness of the upright curb. Curb height is its vertical height. The gutter width is the flat flag in front of the curb, and the flag thickness is how thick that flag is. The calculator treats the flag as running under the curb, which is how curb and gutter is normally cast.

Length is the run along the centerline of the curb. On a curve, measure along the middle of the curb, not the inside edge.

Curb and gutter cross-sectionGutter width + curb depthCurb depthCurb heightFlag thickness
The cross-section area times the run length gives the volume.

The curb and gutter formula

The cross-section is the curb rectangle plus the flag rectangle. The curb rectangle is depth × height. The flag rectangle is (depth + gutter width) × flag thickness, because the flag runs the full width under the curb as well as in front of it. Multiply the section area in square feet by the run length in feet to get cubic feet.

All the section dimensions are in inches. Convert them to feet by dividing by 12 before multiplying. A 6 in curb 6 in high has a section of 0.25 ft², and the flag adds 1.0 ft², so the section is 1.25 ft² for the example below.

Formula: V = (D × H + (D + G) × F) × L × quantity, all in feet.

Worked example: 100 ft of curb and gutter

  1. Convert to feet (inches ÷ 12, centimeters ÷ 30.48): Curb depth 6 in = 0.5 ft; Curb height 6 in = 0.5 ft; Gutter width 18 in = 1.5 ft; Flag thickness 6 in = 0.5 ft; Length 100 ft
  2. Curb section = 0.5 × 0.5 = 0.25 ft²
  3. Flag section = (0.5 + 1.5) × 0.5 = 1 ft²
  4. Volume = (0.25 + 1) × 100 × 1 = 125 ft³
  5. Net volume = 125 ft³ ÷ 27 = 4.6296 yd³ (× 0.0283168 = 3.5396 m³)
  6. Order quantity = 4.6296 yd³ × (1 + 10%) = 5.0926 yd³ = 137.5 ft³
  7. 80 lb bags = 137.5 ft³ ÷ 0.6 ft³ per bag = 229.17 → 230 bags (always round up)
  8. Weight = 137.5 ft³ × 150 lb/ft³ = 20,625 lb
100 ft run, 6 in curb, 6 in high, 18 in gutter, 6 in flag, 10% waste
QuantityResult
Net volume4.630 yd³ (125.00 ft³, 3.540 m³)
Order with 10% waste5.09 yd³ (3.89 m³)
80 lb bags230
60 lb bags306
Weight at 150 lb/ft³20,625 lb

That is 5.09 yd³ for 100 ft with waste. Without waste it is 1.25 ft³ per linear foot, so you can multiply that figure by any length to check a quote.

Curb sections vary

There is no single curb. Barrier curbs, mountable curbs and rolled curbs have different shapes, and agencies publish their own standard drawings. This calculator uses rectangles, which is accurate for a plain upright curb. A sloped or rolled face removes some concrete, so the result is slightly high and safe to order from.

For public work, use the standard detail from the agency. For a driveway apron or a garden edge, the rectangular model is more than good enough.

Practical tips

  • Curb machines and hand forms both need a stiff mix. Ask for a low-slump mix and expect a plasticizer if the plant recommends it.
  • Plan control joints through the curb at the same spacing as the flag.
  • Pour curb and gutter monolithically so there is no cold joint where water runs.
  • For a short run, such as a parking-lot island, bagged concrete is realistic: 10 ft is only 12.5 ft³, about 21 bags.

Frequently asked questions

How do I calculate concrete for a curb and gutter?

Find the cross-section area: curb depth × curb height plus (curb depth + gutter width) × flag thickness, in square feet. Multiply by the length in feet. Divide by 27 for cubic yards.

How much concrete is in 100 ft of curb and gutter?

With a 6 × 6 in curb, 18 in gutter and 6 in flag, about 125 ft³ or 4.63 yd³ before waste.

What is a flag in curb and gutter?

The flag is the flat gutter pan in front of the curb face that carries water along the edge of the road.

Does this work for rolled or mountable curb?

It treats the section as rectangles, so a sloped face is slightly overstated. That is a safe direction for ordering.

How much waste should I allow?

Five to ten percent. Hand-formed runs lose more than machine-placed curb.

Can I use this for a concrete mow strip or edging?

Yes. Set the gutter width and flag thickness to the size of the strip, or set the curb height to zero if your design is flat.

Sources

Estimate only. Results depend on the numbers you enter, ground conditions and your supplier. For structural work consult a licensed engineer and follow local codes. Brand names such as Quikrete and Sakrete are used only to cite published product data. This site is not affiliated with any brand.

Order about5.09 yd³

↑↓ to move Enter to open Esc to close

Share this page

On this page