Concrete Formwork Basics

Forms are the mold that decides the shape, level and edge of your concrete. For a typical slab, use straight 2×4 or 2×6 boards, stake them every 2 to 3 ft and brace them so that they cannot move.

By the Editorial team · How we calculate · Updated Oct 4, 2026

Calculators for this topicSlabFootingWallSonotubeCircular slab

What forms do

Concrete is fluid when it arrives and keeps its shape only if something holds it. Forms provide that support until the concrete has hardened. They also set the top surface level for screeding and the finished edge profile. A form that bows, moves or leaks changes the thickness of the slab and therefore the volume you need, which is why cheap forms often cost more in concrete.

Slab form sectionconcrete (T)gravel baseform boardstakeT
The form board sets the top of the slab. Stakes on the outside keep it in place.

Lumber sizes

Nominal vs actual lumber sizes
NominalActual (in)Use for slab thickness
2×41.5 × 3.5Up to 3.5 in
2×61.5 × 5.5Up to 5.5 in
2×81.5 × 7.25Up to 7.25 in
2×101.5 × 9.25Footings and thick edges

A “4 in” slab does not fit a 2×4, since a 2×4 is only 3.5 in tall. Use a 2×6 and set it so the top is at the finished surface, and the slab edge is 4 in below. Straight boards are best. Check each for bow before use. Plywood, hardboard or flexible bender board form curves.

Staking and bracing

  • Stake on the outside of the form every 2 to 3 ft, and at each side of a joint between boards.
  • Drive stakes below the top of the form so that screeding is not obstructed, and fasten from the outside with screws.
  • Brace corners and long runs with diagonal braces that bear against stakes or the ground.
  • Use screws rather than nails when you want to take the forms apart easily.
  • Backfill the outside with soil to keep the concrete from leaking under the boards.
  • Check the form for position and level after bracing, because driving stakes moves boards.

Setting level and slope

Stretch a string line between stakes at the planned finished height and set the board tops to it. Slabs outside should slope away from buildings, commonly about 1/8 to 1/4 in per foot (1 to 2%). Set the high side first and measure down for the low side. Check with a long level or a laser. Water that pools on a slab freezes into ice in winter and speeds up damage.

Curves

To make a curve, use thin hardboard, plywood strips or flexible bender board. Kerf the back of a board with a series of saw cuts, or soak it in water so that it bends. Stake closely, every foot or less, to hold the curve. Curved edges mean the area is no longer rectangular, so use the circular slab calculator or break the shape into simple parts for the volume.

Release agent and removal

Coat the form faces with a release agent, such as a commercial form oil, so that the concrete does not stick. Do not let it run onto the base or the rebar. Remove forms after a day or two, once the edges have hardened, using a pry bar carefully so that the slab edge is not chipped. Backfill and compact the soil along the edge.

Forms for walls and footings

Walls are much harder than slabs, since fresh concrete behaves like a fluid and presses on the form with a pressure that increases with depth. At a depth of 4 ft, a fluid pressure of 150 lb/ft³ is about 600 lb per square foot at the bottom. Wall forms use plywood panels, studs, walers and ties, and need an engineered design if the wall is tall. A poured wall of 20 × 4 ft at 8 in thick needs 2.17 yd³ in the form, according to the wall calculator.

Footings in trenches can often use the sides of the trench as forms, provided the soil is firm and the trench is cut cleanly; this tends to use more concrete than the drawing. For tube forms, use the Sonotube calculator.

Mistakes to avoid

  • Forms that are not braced and bow when loaded.
  • Setting the tops without a string line or level.
  • No slope for drainage.
  • Gaps at corners that let the paste out.
  • Using warped lumber.
  • Removing forms too soon.

Form materials compared

Choices for forms
MaterialBest forNotes
Dimensional lumberSlabs, footings, stepsCheap and common; reusable with care
PlywoodWalls, wide surfacesUse form-grade plywood and bracing
Hardboard or bender boardCurvesFlexible; stake closely
Cardboard tubesPiers and columnsSingle use; waterproof coating helps
Steel or aluminum formsRepeated use, precisionRented or purchased by professionals

When to remove forms

Typical earliest removal (moderate weather)
FormTime
Slab edge forms24 – 48 hours
Footing forms24 hours
Wall forms (non-load-bearing)1 – 2 days
Stair risers and sides24 – 48 hours
Forms under structural loadsAs specified by the engineer

In cold weather leave forms on longer to hold in heat. Remove them carefully to protect the edges.

Checklist before the truck arrives

  • Forms are straight, level to plan and braced.
  • Release agent is applied.
  • Stakes are below the top of the form.
  • Corners are tight and gaps are sealed.
  • The base is compacted and damp but not muddy.
  • Reinforcement is in place on chairs.
  • Tools, helpers and a curing plan are ready.

Example: forms for a 12 × 12 ft patio

A 12 × 12 ft patio needs 48 ft of form boards (four sides), so five 10 ft 2×6 boards cut to length, and about 24 stakes at one every 2 ft. The slab takes 1.96 yd³ with 10% waste. Stake the corners first, tie the boards with screws, then add the other stakes while checking the level. Drive stakes slightly below the top of the form, brace any bows and check the diagonals to make sure the patio is square: both should be equal.

Frequently asked questions

What wood do I use for concrete forms?

Straight 2×4 or 2×6 lumber for slabs, plywood for walls and flexible board for curves.

How far apart should form stakes be?

Every 2 to 3 ft, and closer for curves.

Do I need release agent?

It is recommended. It stops the concrete bonding to the boards.

When can I remove forms?

Usually after 24 to 48 hours for slab edges.

How do I make a curved form?

Use hardboard or bender board and stake it closely.

Can I use the trench as a form?

For a footing in firm soil, yes, but expect to use more concrete.

Sources

Estimate only. Results depend on the numbers you enter, ground conditions and your supplier. For structural work consult a licensed engineer and follow local codes. Brand names such as Quikrete and Sakrete are used only to cite published product data. This site is not affiliated with any brand.