How Much Concrete for a 30×40 Slab?

A 30×40 ft slab (1200 ft²) at 4 in thick needs 14.81 cubic yards of concrete, or about 16.30 yd³ with 10% waste. In bags that is 734 bags of 80 lb mix. Change the thickness below to see other options.

  • Free
  • No sign-up
  • Math shown
  • Sources listed

Your measurements

Quick sizes

How many identical pieces

%

5–10% is the usual advice. Use more when the subgrade is uneven, forms may flex or spillage is likely.

Advanced assumptions

Yields come from the bag label or data sheet. Check yours: other products (high-strength, lightweight) differ.

Order about16.30 yd³12.46 m³ · 440.00 ft³ · includes 10% waste

Above 2 yd³ ready-mix is usually the better choice. Hand-mixing 734 bags is a long day. Small truck orders often carry a short-load fee, so ask your plant.

Example for the numbers in the form. Change any value to calculate your own.

Volume

Net volume
14.815 yd³
Net volume
400.00 ft³
Net volume
11.327 m³
Order (with waste)
16.30 yd³

Bagged mix (80/60/50/40 lb)

80 lb bags
734
60 lb bags
978
50 lb bags
1,174
40 lb bags
1,467

Weight of the order

Pounds
66,000 lb
US tons
33.00
Kilograms
29,937 kg
Density used
150 lb/ft³

Wheelbarrow loads

3 ft³ barrow
147 loads
6 ft³ barrow
74 loads

Material cost (estimate)

Ready-mix
$2,037 – $3,378
Bagged (80 lb)
$4,037 – $5,872

Ranges, last verified 2026-10-04. Excludes labor, forms and finishing.

Next: plan the rest of the pour

These open with your measurements already filled in.

By the Editorial team · How we calculate · Updated Oct 4, 2026

Prices last verified: 2026-10-04. How we source prices.

Show the math
  1. Convert to feet (inches ÷ 12, centimeters ÷ 30.48): Length 30 ft; Width 40 ft; Thickness 4 in = 0.3333 ft
  2. Volume = 30 × 40 × 0.3333 × 1 = 400 ft³
  3. Net volume = 400 ft³ ÷ 27 = 14.8148 yd³ (× 0.0283168 = 11.3267 m³)
  4. Order quantity = 14.8148 yd³ × (1 + 10%) = 16.2963 yd³ = 440 ft³
  5. 80 lb bags = 440 ft³ ÷ 0.6 ft³ per bag = 733.33 → 734 bags (always round up)
  6. Weight = 440 ft³ × 150 lb/ft³ = 66,000 lb

What this slab is used for

A 30×40 ft slab (1,200 ft²) is the size of a small barn, a workshop, a three-car garage with storage or a pole-barn floor. It is a significant structure that calls for a design, a permit and professional help in most places.

Heavy use favors 5 to 6 in with reinforcement. Pole barns and shops that carry loaded equipment, lifts or heavy storage often use thicker slabs, fibers and engineered base layers. Follow the plans.

30 by 40 ft slab30 ft40 ftThickness (T)
The 30×40 ft footprint is 1200 ft² (111.5 m²).

Concrete for a 30×40 ft slab at each thickness

A 4 in slab is 16.30 yd³ with waste, 5 in is 20.37 yd³ and 6 in is 24.44 yd³, which is 2 to 3 truckloads. The concrete alone weighs 33.00 tons at 4 in. The cost of the concrete is in the thousands, so a 5% error is meaningful. Check the quantity twice and ask the contractor for a breakdown.

30×40 ft slab, 10% waste
ThicknessNet yd³Order yd³Order m³80 lb bags60 lb bagsWeight
3 in11.1112.229.3455073449,500 lb
4 in14.8116.3012.4673497866,000 lb
5 in18.5220.3715.57917122382,500 lb
6 in22.2224.4418.691100146799,000 lb

The formula is 30 × 40 × thickness ÷ 12 ÷ 27 for the net volume. The order adds 10% for waste and rounds the bag counts up. Use the calculator above for another thickness or waste allowance.

Bags or ready-mix for 30×40 ft?

Bags: 734 bags of 80 lb mix at 4 in, a total of 58,720 lb of dry product. Ready-mix: 16.30 yd³, material about $2,037–$3,378 at the published range, last verified 2026-10-04, before delivery and short-load fees. Bagged concrete for this slab costs about $4,037–$5,872. Because the order is above two cubic yards, a truck is usually the practical choice, and at 6 in you may need 3 loads. See bagged vs ready-mix.

What to watch for

  • Underestimating the volume of thickened edges and footings, which can add several yards.
  • Poor communication with the plant on spacing of trucks.
  • A saw-cut schedule that starts too late, so the slab cracks before it is cut.
  • Finishing without enough crew or equipment such as a power trowel.

Layout and joints

Plan access to the site for several trucks, with a place to turn around and wash out.

For a 4 in slab, joint spacing of 8 to 12 ft is the usual range, with a 15 ft maximum for any thickness. Read the control joints guide for depth and timing.

Example joint layout for a 30×40 ft slab10 ft30 × 40 ft slab, joints every 10 ft
One possible joint layout for a 30×40 ft slab. Your plan may differ.

Before you order

  1. Measure the forms, not the excavation, and check the thickness in several places.
  2. Add the volume of any thickened edge, apron or step separately.
  3. Plan the base: use the gravel base calculator to estimate stone for 1200 ft².
  4. If the design calls for steel, estimate it with the rebar calculator.
  5. Put the quantity on the Pour List to combine it with footings and steps.

Frequently asked questions

How many yards of concrete for a 30×40 slab?

14.81 yd³ net at 4 in, 16.30 yd³ with 10% waste.

How many bags of concrete for a 30×40 slab?

734 bags of 80 lb mix or 978 bags of 60 lb mix at 4 in with 10% waste.

How much does a 30×40 slab weigh?

About 66,000 lb (33.00 US tons) at 4 in with 10% waste, using 150 lb/ft³.

How many yards for a 30×40 slab at 6 in?

24.44 yd³ with 10% waste.

How much does a 30×40 concrete slab cost in materials?

About $2,037–$3,378 for ready-mix concrete at 4 in, before delivery fees, based on the ranges on the cost page (verified 2026-10-04).

Sources

Estimate only. Results depend on the numbers you enter, ground conditions and your supplier. For structural work consult a licensed engineer and follow local codes. Brand names such as Quikrete and Sakrete are used only to cite published product data. This site is not affiliated with any brand.

Order about16.30 yd³